|

| |
.jpg) |
The new ministry campus at
the Meadows of Granby that
will be central to the Pioneer Valley. It is
accessible from Holyoke (5 miles), South Hadley (2 miles),
Belchertown (8 miles along US 202), Chicopee (3 miles from
MA 33-Memorial Drive), Amherst, Pelham, and Hadley (8-15 miles along
from MA 116).
Scroll down the page
to see the progress (latest to earliest)

|
May 8, 2008
- Most all work necessary to obtain a Certificate of
Occupation has been completed.
- This week: lightening rods connected, restroom dividers
installed, carpeting laid, door sills replaced, porch posts
sheathed, finish plumbing inspected, fire extinguishers
installed, audio chases framed and plastered, fire blocks at the
electric box installed, water heater relay activated.
|
|
- March, 2008 - We're about ready to commence worship services
in the main hall. Heat, plaster, electricity and water are
functioning.
|
 |
 |
- February, 2008 - We are on the penultimate push. Spray
foam insulation (reducing heating demands 30%-50%; & air
exchange down to 0.6 cf from 3.2/hour). Next dry wall and
plaster, then heating and propane. Hardware and door will
soon follow.
|
- October 4, 2007 - We've hit a holding pattern as we wait for
the doors to arrive and for an engineering approval for
repositioning a roof truss member that has to be cut to
accommodate a heating duct. It's been a good run for the
past eight weeks and much has been accomplished. We are
sill looking to begin occupancy in December (but praying for
November).
|
 |
|
|
- September 16, 2007 - Believe it or not,
the first hymn to God was sung in the main
hall this Sunday: Psalm 23 to the tune of
EVAN! We recessed our scheduled worship
at the Legion Hall and
caravanned over to the land to inscribe
scripture passages and prayers on the
framework. Don't miss the excitement
and inspiration in the weeks ahead as we gradually shape the building for
reaching the world as Christ's ambassadors.
|
|
 |
 |
 |
- August, 2007 - Utilities conduits, waste water lines and the
septic are in place. Framing should begin as soon as the
rough grading is completed this week.
|
 |
 |
|
July 2, 2007 - The footings and foundation have received the Building
Inspector's check! Pastor Rodkey met with the heating and plumbing
subcontractor to review the heating system. We are looking at an on-demand
boiler with a three staged, ganged heat exchangers. This is
estimated to be 94% efficient, and beca use of the irregular demands for heat in
a church, more suitable than the hydronic PEX system first considered.
|
- June 18, 2007 - Foundation Forms are being installed by Bob,
Forest and Adam!
|
 |
 |
THE EXCAVATION PERMIT IS IN HAND!!! It only took 362 days
WE'RE
ROLLING!
OUR TARGET DATE TO RECONVENE CONSTRUCTION IS now APRIL
MAY 9, 2007 how about June 5, 2007
|
|
We're finally back at it. The center for
Ministry, Worship, Outreach is underway! |
- June 8, 2007 - The footings are in!
|
 |
|
|
|
-
March 20, 2007 - With the Conservation Commission approval
on March 13,
2007, we successfully drilled a 250' well with a water flow of 30
gallons/minute! This week the
Granby Health Department will make a second review of the septic system design.
|
- March 14, 2007, just before the spring thaw, we were able to
get the boring rig onto the land and successfully drill
the well. "Ready for many-a-baptisms now!"
|
 |
We're on a roll! On
Oh no! Conservation concerns over the disturbed soil
have caused us to pause briefly while we get some advice and a few permits.
The public hearing for the review was to have been on November 14, 2006., but
had to be rescheduled for November 28, because of no-quorum.

The driveway to the Ministry Center is started! October 18, 2006
The police detail for October 15 observed the sightline for oncoming
traffic was a bit tight. They suggested we shift the driveway as far east
as possible to gain a few extra seconds of visibility. Russell Street
Builders did just this. The new driveway will have a slight curve to it; a
bit Zen like.

The Ministry Center will be on a thirty acre field at 160 West State Street in Granby,
Massachusetts; central to the Pioneer Valley mission field.
Click here to view a satellite image of the field...


This rendering gives an idea of what the new ministry facilities will
look like. Although it is rudimentary, you can see the concept of a
multifunctional hall with a deck, and the attached ministry/mission wing for
outreach services and discipleship development.

The design is for each room to be multi-functional. The assembly hall
serves as worship space, lecture hall, dinning room, youth fellowship activities
center. The coat room doubles as storage in the summer. The nursery will
accommodate both infants and toddlers. The kitchen hosts both catering and
in-house cooking. The music room can be divided into two classrooms with
ample storage for instruments and teaching aids. The unisex restroom is
handicap accessible, plus it will hold a shower for visiting mission teams our
youth overnights, as well as allow the grounds keeper to clean up before heading
home. The reception area is a place for greeting as well as a warm, dignified
space for recipients of food assistance and the like.
|